Wooler Water Treatment Works

As part of our ongoing investment programme and to ensure the highest level of customer service, we are constructing a new Water Treatment Works (WTW) at Wooler, Northumberland. The new WTW is located in the town of Wooler, at a site opposite Berwick Road Industrial Estate . The main construction phase commenced in summer 2020 and was substantially completed in autumn 2021. Final commissioning to bring the new WTW into service is currently scheduled to run through until autumn 2022.

Update by Joan Tatters

Good Morning,

Oh my it's definitely Winter isn't it!!!

This weeks update:-

Treatment building: -

The 1st lift blockwork to the west and north-west of building externally is progressing although the weather is affecting progress however its allowed the skimming of welfare are to be complete a little quicker. The first fix of electrics is done too!

We are continuing to install the cabling within the building and the gantry work is very impressive as the photos shows, they house the cabling. 

The security doors have been installed on the north side.

 

 

 

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers