Wooler Water Treatment Works

As part of our ongoing investment programme and to ensure the highest level of customer service, we are constructing a new Water Treatment Works (WTW) at Wooler, Northumberland. The new WTW is located in the town of Wooler, at a site opposite Berwick Road Industrial Estate . The main construction phase commenced in summer 2020 and was substantially completed in autumn 2021. Final commissioning to bring the new WTW into service is currently scheduled to run through until autumn 2022.

Update by Joan Tatters

Good Morning All,

Didn't get an up date in last week so it's a little late........apologies.

Well the weather was rather cruel wasn't it, we were challenged to say the least  with temperatures of -13c, even the generator kept cutting out so there was not welfare for the team. Gary and the team had no power and a frozen water supply and therefore the site was shut every morning from 9.30.

That said some work did happen:-

Deliveries did eventually get through on certain days, internal painting, some cabling and pipework was done albeit limited due to the conditions.

Sorry no photos this week but there will be in the future.

Wow, what a week!

Stay safe and warm everyone.

 

 

 

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers