Update by Kevin McGargle
Good afternoon,
I'm Kevin McGargle the site manager for MMB who is in charge of completing the works on this scheme. You may have noticed our presence back on site completing works to the recently installed sewers, we are now currently grading up the working area ready for the import of topsoil commencing Monday 25th April 2017 for a duration of 4 days. we will have a large number of wagon movements in and out of Middle Engine Lane during this period so please be cautious in this area.
Thereafter we will be carrying out finishing works to the manhole covers, removal of the fenced boundary and landscape seeding works.