The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
11°C

Bewick Park, Wallsend

The Bewick Park project is being carried out to reduce the risk of internal flooding to four properties on Bewick Park. Our construction works will start on 11th July 2016 and will take approximately 22 weeks to complete. The works will involve the installation of new sewer pipes on Bewick Park, Addington Drive and Middle Engine Lane. Our experienced partner, Mott Macdonald Bentley, will be carrying out this work on our behalf and they will contact you with more information about the project if you are going to be directly affected by our works.

Planned works

WE WILL BE INSTALLING 335 METRES OF PIPE TO IMPROVE THE PERFORMANCE OF OUR SEWER NETWORK.

This work will involve installing new sewer pipes in the highway and, as a result, some traffic management and phased road closures will be necessary. We are working closely with North Tyneside Council to make sure any disruption is kept to a minimum.

We will also be constructing a temporary site compound within public open space on Addington Drive.

WHERE WE WILL BE WORKING

Area of work Start date End date Additional information
Addington Drive (West side) 11/07/2016 02/12/2016 Our site compound will be constructed here within the public open space to the rear of 38 to 50 Bowness Avenue and will be in place for the duration of the work.
Addington Drive (East side) 06/10/2016 14/11/2016 We will be installing new sewer pipes within the highway verge. It will be necessary to close the public footpath whilst this work is being carried out.
Junction of Addinton Drive and Bewick Park 21/07/2016 23/08/2016 Three way traffic lights will be in place while we install new sewer pipes.
Bewick Park between numbers 1 and 7 Bewick Park     A phased road closure will be in place while we install new sewer pipes here.
Middle Engine Lane 10/08/2016 10/10/2016 We will be installing new sewer pipes within the highway verge. It will be necessary to close the public footpath whilst this work is being carried out.
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers