Update by Gabrielle Ward
Good afternoon,
Since our last update the site team have commenced with constructing the Chemical Dosing Kiosk slab and delivery area ready for the kiosk to be delivered in May. The concrete has been poured, and our subcontractors, North East Site Services, have installed the tarmac infills either side of the road. In this area, the drainage gully has been installed along with the downstream pipework.
Exavation works have been carried out for the Tertiary Pumping Station, and the concrete base has been poured.
I have included some photos for you to view.
Please leave a comment below should you have any questions, and a member of the project team will get back to you.