Update by Bethany Oakley
Good afternoon,
I hope you’ve all had a great weekend.
Over the last few weeks, we have continued to make some great progress on the Treatment Works.
The existing sludge tank has been demolished and a new one is currently being constructed.
The concrete base has been poured for the Primary Settlement Tank and the wall is currently under construction.
We have also installed the new Sludge Tank Hopper Pipework.
I have also added some photos so that you can see the great work the Team have carried out.
As always, if you have any questions you’d like to ask us, please add these in the comment box below and a member of the Project Team will respond.
Speak soon!
Bethany