Update by Sarah Jayne Parvin
Good afternoon all, works are progressing well on site ground stabilisation works are complete and the concrete bases poured, this is where the dosing plant kiosks will be installed. We are almost ready for delivery of the kiosks on the 21st June.
In preparation for the delivery of these 4m wide kiosks, we need to carry out some work along the site access track. Which include tree pruning and temporarily relocation/removal of fence posts to give us the clearance required. This work will be carried out by our contractor Marleys on Monday 13 June.
On the day of delivery the kiosks will be traveling through Thomas Swans site so there is no requirement for vehicles to be moved of the roads surrounding the site access.
On behalf of the Project Team, we would like to thank you all for your patience and support during our essential work.