Update by Shafqat Akbar
Hello everyone. Our site teams have completed a lot of work since my last update. I want to tell you about the good progress that we have made. The works at the Dilstonhaugh site have progressed very well over the past month. We have started constructing the new shaft. Progress is good and we have alrady installed six of the ten precast concrete rings that make up the main structure. We will start the mechanical and electrial installation once the shaft is constructed and is water tight.