Update by Becky Gartland
Good morning everyone,
Please see attached some images of our progress on site so far.
The shaft of the pumping station is almost complete with the last remaining rings to be installed by the middle of next week. Once all rings are in place there will be a concrete plug installed along with the concrete base within the structure. This will be carried out over the coming weeks.
In terms of the drainage installation within the carriageway of South Terrace, we are continuing to progress well with a third of the overall pipework having now been installed. As mentioned yesterday the reinstatements of this initial section will be completed on Saturday 10th July ready for the traffic managment to be moved along to the next section of carriageway on Monday 12th July.
Hope you all enjoy your weekend and fingers crossed for a good result for England on Sunday!
Becky