Update by Christine Taylor
Good mornning
Please see below the update provided by site
- Legato concrete blocks are being installed into Reservoir Embankment for long term stability
- The drainage works and filling operations being undertaken to rear of Legato Blocks
- Materials being screened on Borrow Pit Area to process further selected materials for use as suitable backfill on Reservoir Embankment.
- Translocation of existing trees to new planting area of Northern Embankment
Have a lovely weekend
Christine