Update by Julie Oakley
Good afternoon All,
We are pleased to share the progress made on the project this month:
Works are progressing well here at Slaley, the Soneco unit which is a liquid chemical-free water treatment system has been successfully delivered to the site, along with both the motor control centre (MCC) kiosk and they are ready for installation we use this to treat the wastewater, the excavation for the humus settlement tank is now fully shored, and the base slab has been poured, this is used in the final process of the water treatment system. We are on with installing the piling and excavation work is underway for the Primary Settlement Tank (PST) which is one of the wastewater treatment processes and we have also started repairs on the existing settlement tank.
If you have any questions or issues please feel free to leave a comment below or use the details provided to contact us and one of the team will be happy to help.
thank you you for your support while the works are on going.
Julie