Update by Karen Alexander
Good afternoon,
We’re continuing with our preparation work along the pipeline route, and we’ve arranged two short-term road closures in conjunction with Durham County Council in the coming weeks.
The first of these will take place from Monday 5th February to approximately Sunday 11th February 2024 on the B6279 to the west of Ingleton.
The second road closure will take place from Monday 12th February 2024 to approximately Monday 19th February 2024 on the road between the B6279, to the west of Ingleton, and Hilton.
With all construction projects, unexpected delays can sometimes occur. However, we will not start the second of these two closures before the first one is finished.
Please be assured that we’re working closely with our partners to do all we can to minimise any disruption for you and your community throughout the work. We’ll be working as quickly and as safely as possible and thank people for their patience while this essential work is happening.
Typical working hours will be between 7.30am – 6.00pm, Monday to Friday and 8.00am – 2.00pm on a Saturday.
We’ll be placing roadside signage at the road closure points to clearly signpost the diversion routes.
If you’d like to speak to a member of our project team, you can telephone our customer contact centre on 0345 717 1100 or tweet us on @nwater_care and we will be very happy to help you.
Kind regards
Karen Alexander
Farrans’ Community Business Partner