Update by Rachel Rutter
Good afternoon,
The team have now completed the drainage from the discharge chamber to the settlement tank while the connection of pipework and valves to the discharge chamber are ongoing.
Further pipework is being installed this week and the removal of the existing chamber. Once complete the existing settlement tank will be cleaned.
Thank you for your time, have a great week!
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel