Together with our supply partners Esh Stantec we plan to carry out improvement works to Tunstall Reservoir during 2023. These works are needed to ensure the resilience of the reservoir.

Update by Rachel Rutter

Good morning,

Hope everyone is well. 

The new 600mm diameter pipework for the siphon has been pressure tested and passed with flying colours!

Base and walls have been completed on the penstock chamber and the team have installed the new access into the settlement tank. New monitoring pins have been installed on the dam crest.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you for your time.

Rachel

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers