Update by Rachel Rutter
Good afternoon,
Hope everyone has had a lovely week!
The team this week have constructed the new flow meter chamber at Plawsworth Sewerage Treatment Works (STW) and wet well chamber within Pity me STW. The air valve and washout chambers are nearing completion from Plawsworth STW to Rotary Way.
The gravity sewer pipework is now installed to the west side of the main railway line with reinstatements to the fields being completed once weather conditions improve.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel