Update by Rachel Rutter
Hello everyone,
In the last week the team have excavated and installed ducts and drawpits for MCC kiosk and generator slabs within Plawsworth STW and Pity STW.
Topsoil reinstatement is now complete between Plawsworth STW and Rotary Way, with rotavating and seeding to follow. Reinstatement of works within other areas have also begun including Chester Low Road.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Have a lovely weekend!
Rachel