Good morning,
As mentioned in my previous update the installation of pipework to flow meter chamber is ongoing, with the generator, MCC Unit and Kiosk fitted.
Rotavating of topsoil and seeding is underway including the installation of galvanised ladders to chambers.
The pipebridge substructure piling works are now complete as well as the reinforced concrete roadway.
The woodland area is nearing competition for reinstatement, with Mowing strip works currently being carried out.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you have a great weekend!
Rachel