Update by Rachel Rutter
Good morning,
Within Plawsworth Sewerage Treatment Works the team continue with installation of pipework and cabling to various chambers and MCC Kiosk as well as permanent electrical works within the Kiosk and MCC.
Esh Stantec have completed the backfill of the flow meter chamber ahead of the concrete slab reinstatement. The team continue to remove the easement fencing from the land area before, hand filling of post holes with suitable topsoil.
Rotavating of topsoil and seeding is underway with the installation of galvanised ladders to chambers completed.
Within Pity Me Sewerage Treatment Works the installation of pipework and cabling to the valve chamber and flow meter chamber continues into next week.
The reconstruction of wet well collar to suit anti floatation requirements has been completed, while the team continue to construct the roof slabs for the flow meter chamber.
Gravity sewer pipework is now installed and work has commenced on the under track crossing which will take place over the next 2 weeks. The reinforced concrete roadway is complete as part of Brasside Sewerage Treatment Works.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you for your time
Rachel