Update by Rachel Rutter
Good afternoon,
Esh are nearing completion of benching to interior of Flow Meter Chamber while continuing with drilling and dowelling the existing concrete slabs for reinforced concrete reinstatement works within the Sewerage Treatment Works.
Removal of temporary hardstanding area adjacent to works easement area has begun with a partial area to remain to provide Northumbrian Water tankers access until reinstatement within works are completed.
Within the last few weeks, the interior benching of the valve chamber, installation of ducts and draw pits and the reinforced concrete cover slab to valve chamber have been complete.
Preparation to construct the new concrete roadway adjacent to new structures is underway.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you for your time
Rachel