Update by Rachel Rutter
Good afternoon
Hope you are all well!
The team has now removed the main compound and have begun to reinstate the area.
Joint sealing to the concrete slabs is ongoing including benching within manhole chambers.
Concrete roads are being repaired, and preparation has begun for the tarmac repair.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you
Rachel