Update by Sarah Jayne Parvin
The last few weeks has seen our team complete investigatory works on existing assets and remove abandoned underground structures. We’ve also had diversionary works of an overhead BT line carried out to enable safe excavation of ducting for new electrical feeds to the site. In the background the team have been working hard to deliver design drawings to the site team and the next few weeks should see the team complete civil works for the new kiosk as well as the commencement of excavations for a our new Primary Settlement Tank. Hopefully this is the start of some fine weather which will help the site team make some good progress.
If you have any questions, feel free to leave a comment below, and a member of the project team will respond.
You can also reach out to the MMB Customer Team at MMBcustomerserviceteam@mottmac.com.
Thanks
Sarah