Update by Bethany Oakley
Good morning, everyone,
Following our previous update last month, I thought I'd jump on and give you a further update on the progression to the Aldbrough St John STW.
As always, the Team have been working hard and in doing so, the construction of the PST base has now been completed (photos below) and the contractor, Goodwins are lined up to install the PST – this will be carried out week commencing 2nd September.
The Team have also commenced work on the new storm pump plinths and access road along with starting to plan the first couple of pipe connections to the existing pipe work.
We are hoping to have all the supporting metal work in place for the Inlet works and MCC Kiosk by the end of next month.
I hope you all enjoy the rest of the week. If you have any questions you’d like to ask us regarding the work, please add a comment below and one of the Project Team will respond as soon as possible.
Thank you,
Bethany