Update by Julie Oakley
Good afternoon,
I hope we are not causing too much disruption to the village, I thought I would touch base and provide you with an update with the progress on site,
The site is now fully functional with the MCC and NPG kiosks installed, the excavation and sheet piling for RBC 1 complete and we are ready for base slab pour, we have received the delivery of the SPEL tanks, with the Storm returns pump slab complete.
Works upcoming in next month:
We are to Install RBC 1 (Tuke and Bell mobilising 5th July), the SPEL tank installation and we will Commence with RBC 2 and 3 excavation.
We would liike to thank you for your continued patience and cooperation. If you have any questions or concerns please leave a comment below or use the details provided to contact us and a member of the team will get back to you.