Update by Julie Oakley
Good morning,
I hope you are all looking forward to the bank holiday weekend and enjoying this gorgeous weather, I thought I would touch base with an update on the progress of the works in your area
the works are progressing well and the site is all set up with the cabins in place, good news is we have scaffolded out the MCC and made safe the access, pulled back the spoil heap from the site boundary, we have stoned and blinded the inlet excavation, dug and poured the storm pumping station base and the ducts and chambers from the MCC to NPG are now in place, we are expecting the MCC delivery which is fairly large to be delivered on the 3rd June.
I hope we are not causing too much disruption and we thank you for your patience, if you have any questions or concerns please leave a comment below or use the details provided to contact us and a member of the team will get back to you.
thanks again
Julie