The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
6°C

Arkley Crescent, Hartlepool

We are working with communities to proactively manage flood risk. We’ve identified a flood risk reduction opportunity in the Arkley Crescent and would welcome your views.

Update by Joan Tatters

Hello

Just a quick update as we trott along.... getting closer and closer to the end!

You will have noticed by now in King George Field the work is progressing well, the topsoiling and reinstatement work is really starting to take shape, so much so we are anticipating to complete all work within the field by the end of next week.

On Miers Avenue, all pipework within the carriageway and the reinstating of the tarmac will occur next week which will ease the traffic, we will then progress up Bruce Crescent for the upgrade of the next round of sewers.

Again, thanks to you all for your patience and have a great weekend.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers