Hi I hope you all remain well
I would like to advise of our progress since my update earlier this month. We continue to work closely with Hartlepool Water, Northern Gas Networks and National Power Grid and have agreed the diversionary work required on their networks to avoid clashes with our new sewer. This enabling work will be undertaken in advance of the sewer installation. The programming of this work is yet to be agreed however we anticipate it will commence in June with the main sewer scheme to follow in July taking approximately seven months to complete.
I will keep you informed of any programme changes as we progress. Should there be any issues during the enabling works the respective utility company should be contacted
The sketch posted on the planned works tab shows the location of the proposed new sewer. We will construct a new storage tank to the rear of Arkley Crescent and you will see we are also increasing the size of sections of the sewer in Arkley Crescent, Miers Avenue and Bruce Crescent.
I will be in touch again with more scheme specific and traffic management information closer to the construction start data.
We will continue to engage with the local community seeking your views and addressing any concerns you may have. Please leave your comments on this update or get in touch using the “Contact us” button at the top of the page. Alternatively if you would like to contact me by telepnone, now or during the work, please contact our Customer Contact Centre on 0345 717 1100 to request a call back from the Project Team. I hope to hear from you soon.
Thanks Again