Arndale House, Birtley

We are planning work to reduce the risk of flooding and improve the performance of the sewer network in Birtley.

Update by Sarah Jayne Parvin

Good morning, im up on site this morning, catching up on the progress made since my last post.

Work is progressing well and we are currently ahead on our programme. We have a team continuing work in the car park near the taxi rank, laying the pipe to connect to the new pipe we installed across Durham Road. 

Preparation works to clear vegetation, trim back trees and bushes between St Johns Place and Arndale House have started ready for our team to lay a new surface water pipe. We are expecting the pipe laying to start mid to late October but will confirm this closer to the date.

Thanks 

Sarahjayne Vickers

MMB Liaison Officer

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers