Update by Shafqat Akbar
Hello everyone. After yesterday's successful operations at the Bellingham treatment works, I want to update you on the next phases of our project.
We will set up, test and commission the temporary plant on the site. This will take a couple of weeks.
The replacement of the filter media will commence after the temporary plant is operational.
The site team have agreed a programme of works with Northumbrian Water and discussed the interventions required into the existing treatment works.
The treatment works will remain operational at all times during the project. We will keep our neighbours informed of any works that might affect them.