Update by Shafqat Akbar
Hello again. I want to update you on the works that are happening at the Bellingham site. We will be replacing the filter media in the existing filter beds and refurbishing the the exising filter tanks.
The site team recevied the temporary filter treatment equipment two weeks ago. We have installed this equipment and are letting the filter media "seed" before we divert the sewage flows through the temporary treatment. It's all going to plan
The next phase will be to divert the flows and start working on the existing filter beds.
The site teams will carry out the refurbishment works to the existing filter beds. We will replace the tiles at the bottom of the filter beds and place new filter media into the tanks.
The site works will be carried out without affecting our neighbours. We will have some additional deliveries to the site.