Good afternoon,
Since our last update, the site compound area has been stripped of topsoil and laid with terram and stone. The site cabins are now set up and are fully operational with the water and electrics connected.
The team have dug out and stoned up the area ready for the concrete base to be poured where the new Haigh Inlet Screen will be installed. This will filter and treat the incoming flows.The existing pipeline has also been exposed and surveyed.
Please leave a comment below if you have any questions, and a member of the project team will get back to you.
Thanks
Gaby