Update by Bethany Oakley
Good morning,
I hope you are well.
Further to our last update, we have made some progress to the works that I’d like to share with you.
The storm returns and site returns pipework is now 100% complete and has passed their tests ready for us to turn the flows.
We have also completed the balance tank footpath meaning all structural works are now complete.
The balance tank outlet pipework is also 90% complete and the flume to the existing works pipework’s is 100% complete.
Our Site inlet pipework has now commenced, and I am pleased to advise that most of the remedial works and landscaping work has already been carried out and is complete, in readiness for the demobilisation.
We will share any further details that we think are relevant prior to the demobilisation on Site and answer any questions that you may have – please add a comment in the box below and a member of the Project Team will respond.
Take care and enjoy the rest of your week!
Bethany