Update by Sarah Jayne Parvin
Good morning all, it’s been a while since I provided you an update, so here goes….
We are currently working to programme and all being well the work should be compete week ending 26th October 2018.
The concrete repairs in the Distribution Chamber are complete. Over the coming weeks we now need to restore the chamber back to its original pipework, to restore the flows back to the original state and remove the pipe work diversion we put in place.
If you have any questions please don't hesitate to use the 'contact us' button at the top of this page.
Thanks
Sarah