Update by Shafqat Akbar
Hello everyone. I want to give you an update on the progress we have made at this pumping station.
Our project is substantially complete. Our site teams have completed the works and demobilised from site. We need to plan our return to complete the reinstatement of the grass areas where we had our site compound, storage areas and access road.
We have temporarity cordoned off an area of the site to allow our landscpae contractor carry out the remaining reinstatement works.
The pumping station remained fully operational during our project. We need to arrange a date when it will be suitable to carry out the remaining snagging works at locations where we tied into the existing pumping station plant and equipment.
This photograph shows the pumping station building at the pedestrian walkway level. We have completed all planned works inside the pumping station. We need to finish off some minor snagging items at the pumping station.