Update by Rachel Rutter
Good Morning,
Hope everyone is having a great week!
This week the team are pressure testing for the new 600 diameter cross connection pipework to be completed to 7.0 Bar.
Scaffolding works to one half of the Bellmouth & remedial works have commenced and the existing chamber clay stank, excavation and installation of the clay is now complete.
If anyone would like to discuss our works in more detail, please feel free to contact us by commenting on this post or sending an email to nwl.customer@esh.uk.com.
Thank you
Rachel