Update by Rachel Rutter
Good morning,
The team have recently completed works to the new storm overflow pipe and the final connection into the existing storm overflow chamber has been made and is ready to receive flows once the rest of the works are complete.
This week the crew have commenced works to install the new storm return rising main, with the concrete beening cut along the length of the trench and excavation works ongoing. Next week they will be continuing with this work and start installing the pipework.
Thank you for your time. Have a great weekend!
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel