The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Castle Hill Farm Cottages

An application has been submitted under Section 101A of the Water Industry Act 1991 for provision of a public sewer for premises at Castle Hills Farm Cottages, Berwick. The application complies with the requirement criteria, Northumbrian Water plan to undertake works to reduce the environmental risk improve the resilience and enhance the performance of the sewerage network serving the residents of Berwick. This project aids NWL in improving the quality of rivers and coastal waters, the environment and wildlife for the benefit of our customers.

Update by Christine Taylor

Good afternoon,  

I have managed to catch up with the site team for an update.  Paul Jones who is currently on site and has advised the drainage across the road is now completed.  They are currently constructing the new manhole in the verge.  The trenchless section of pipework in the field is now installed.  Our team will be starting the open cut section of sewer to tie into the new manhole in the verge,  

I hope you all have a lovely weekend.

Christine

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers