We have had a change on site. Jordan Richards is now providing our updates and looking after the site. He has kindly updated us this morning.
Since the 4 October works have been undertaken to progress with the rising main installation which is set to be completed and pressure tested by the end of this week. Traffic management on the road was removed on the 5 October. To enable the team to complete the outstanding reinstatements we will need to re-establish the traffic lights for a couple of days. This work is planned on the 7 November.
Next week the work on the new retaining wall structure at the pumping station will commence.
We will endeavour to keep you updated with our progress.