Good morning all,
It's been a while since you were last provided an update regarding our works so just wanted pop on and get you up to date.
Over the past few weeks the site team have continued with the drainage installation of the new surface water sewer line within the carriageway. Work has also commenced on installing the new drainage lines within property boundaries which will be backfilled before we break up for the Christmas Period.
Within the pumping station work has been carried out to install the stone cladding to the retaining wall along with completion of the filter drain being installed. Works have been ongoing following this to bring the ground levels back up to the existing height. Final works in this area are to install the spring assist covers and frames along with the concrete hard standings.
From today our work will be suspended for the Christmas and New Year Period and we will resume on Tuesday 4 January 2022. The Customer Team will remain operational during this time, so if you have any site related queries, please get in touch with us.
We would like to take this opportunity to wish all our customers a Merry Christmas and all the very best for 2022!
We would also like to thank you all for your patience and understanding whilst we have carried out our works in your area.
Thank you