Good afternoon,
Since our last update, the site team have been busy setting up our new compound area. The stone laydown area has been laid, and the site cabins have been delivered and are now up and running.
The area for the new Northern Power Grid (NPG) Kiosk has been dug out and ready to be stoned up in preparation for the concrete base to be poured. Once we return to work after the Christmas Break, the new kiosk will then be installed. The new access road area has also been dug out ready to be stoned up.
The site will be closing down for the Christmas break from Wednesday 20th December until Tuesday 2nd January.
On behalf of the project team, we hope you all have a wonderful Christmas and New Year!