Update by Gabrielle Ward
Good afternoon,
I just wanted to let you know how our site team are progressing with the construction work at Chilton Lane STW.
- The sub base (capping layer) to the concrete road has been installed.
- As mentioned in our last update, the Northern Power Grid Kiosk is now complete.
- The bases to the Mecana, NSAF and Chemical Dosing Tanks that improve the quality of the flows and capacity of the works have been dug out and stoned up.
- The ducting works which feeds cables around the works are currently ongoing.
- The Primary Ferric Dosing Point of Application (POA), Secondary Dosing POA and Caustic Dosing POA have been completed (see photos for reference). This area of the STW adds chemicals into the flows to ensure its treated to a high standard.
- The Mecana blinding has been poured ready for the concrete base slab to be poured next week
In the next month or so the MCC trough will be installed, the under slab works to the NSAF will be carried out, the team will continue with the ducting works and the drainage works will be constructed for the Mecana.
I have included some photos for you to view.
Please feel free to leave a comment below should you have any questions and a member of the project team will get back to you.
Please Login in order to comment on this update.