Update by Anya Lowes
Good morning,
I just wanted to give a quick update on the site teams progress over at Chilton Lane STW.
- The final infill for the Chemical dosing has now been completed.
- Our paving areas on site are now 100% complete.
- Although the weather has been quite challenging, when there has been opportunity all planned tasks have been fulfilled.
- Formwork for the Mecana (MCC) has been completed this week and the concrete has been poured ready for the kiosk installation.
In the next month the team will be installing the MCC/kiosk and enabling works will begin for the pumping station construction.
I have included some photos of the progress.
As always feel free to leave a comment should you have any questions, and a member of the team will get back to you.
Thanks
Anya