Here's the latest update on our Chilton WTW project:
- The cofferdam to the pumping station is complete, and the shaft has been constructed.
- The Motor Control Centre panel has been installed on schedule, with Intelect on site for pre-cable work.
- We've finished 80% of the main site excavation and drainage, allowing us to reduce our plant equipment.
- We've also done several pours to improve the pumping and filtration process.
I've attached some photos to show our progress.
As always, if you have any questions or comments, please let us know, and someone from our team will get back to you.