Update by Anya Lowes
Afternoon,
Here is our latest update for Chilton Lane STW:
- We are continuing to downsize our plant where necessary to utilise 90%.
- Our pours for the chemical dosing slab and footpath have been completed.
- The pipework to the Mecana (Motor Control Centre) is also complete.
- The pumping station valve slab and upstands have been poured.
- When on site our subcontractors have switched to using the main power which reduces the need for temporary sources.
If there are any questions don't hesitate to reach out.