Update by Anthony Birkett
Hi Everyone
We're moving ever nearer to Cone Terrace. This week we're working on the manholes in the footpath south of the burn and will reach Cone Terrace on Monday 23 September 2019. This will result in two way traffic lights in Cone Terrace for up to three weeks. We had expected this to take four weeks, but managed to reorganise a little and save a week. We'll work as quickly as we can to get the road fully open again.
I've attached a couple of recent photos.
Regards
Tony