The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
-1°C

Consett Sewage Treatment Works Upgrade

Our proposed refurbished assets will allow us to remove more water from the sludge bi-product that is created when we clean the wastewater at Consett Sewage Treatment Works. The assets will reduce tanker road journeys thereby protecting and enhancing the environment. Our sewage treatment works aids NWG in improving the quality of rivers and coastal waters for the benefit of people, the environment and wildlife.

Update by Grant Crawford

Just a quick update on progress at Consett STW.  Before Christmas we completed the demolition of the redundant sludge handling plant at the location of the proposed new sludge storage tanks. We have also undertaken surface water drainage improvement works along the private access road leading to the sewage treatment works, this work is ongoing and should be completed within the next two weeks.  We anticipate starting below ground drainage pipework and ducting associated with the new sludge tanks shortly.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers