Update by Kevin McGargle
Good afternoon, just to further gary's update recently in that the works are now nearing completion, planned works in the forthcoming week are to restore the currently out of use Clean & RAW water mains back live, this will enable ourselves to then remove the bridge scaffolding and reinstate the land to what its previous use was.
Kind Regards
Kevin McGargle - Site Manager