The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
0°C

Cotherstone Repair, Barnard Castle

We will be investing £800,000 in our strategic trunk mains network. The planned works are made up of the refurbishment of a pipe bridge and the repair of one of our large diameter raw water pipes.

Update by Joan Tatters

Good Afternoon

It's been a little while since my last up date as we wanted to give you a full update of how the project was progressing. I guess we have been on site a lot longer than anticipated however at the turn of the year we will have some definiative dates for completion where we can inform you all of all the work we have achieved both on the pipe bridge and within the village! Yes you are right we have been doing some work at the school.

All will be revealed in January so "watch this space"

Wishing you all a very Merry Christmas and a Healthy 2019.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers