Update by John Young
Removal of Old Chemical Dosing Tank
TDCL decommissioned the chemical dosing tank by flushing and cleaning, it was then diluted and dispersed in to NWL existing wet well with NWG approval. TDCL then employed a specialist subcontractor to safely remove the tank from site for disposal at specialist facility.
Installation of new chem dosing tank and shower
Further to the removal of the existing tank, TDCL installed and commissioned the new Chemical Dosing Tank and Shower unit.
Valve Chamber Lid Install
TDCL appointed subcontractor Technocover to install the security rated valve chamber lid. With TDCL installing a concrete surround for additional aesthetic finish and additional security.
Tie in new pipework to existing rising main
TDCL excavated to formation and installed the requisite pipework, from there TDCL subcontractor UTS attended site to break in to existing rising main via hot tap to complete connection.