Update by Sarah Jayne Parvin
Good afternoon all, time for another update ready for MMBs festive shut down which starts on Wednesday 23rd December till 4th January 2021.
Whilst much of our work is now complete, we still need to return in the New Year to do some final tidying up.
Old Elvet will include installing the traffic island outside of Hotel Indigo, removal of rock and replacement of the topsoil at the site compound at Green Lane and resurfacing the parking bays at Elvet waterside, the resurfacing will be done overnight on the 6th January, a road closure will be in place overnight.
Walkergate there are final reinstatements to complete which will also be carried out overnight starting the evening of the 6th January, again a road closure will be in place overnight.
We will keep you update of our progress in the new year.
We would like to take this opportunity to thank you for your patience and understanding while we have been carrying out this essential work and would like to wish you a peaceful Christmas and New Year.
Thanks
Sarah