Together with our supply partner, Interserve, we plan to carry out work to the Sewage Treatment Works at Elton from Monday 18 February and Friday 15th November 2019. This work is part of a £2 million project of improvements at various sites throughout our network and we are working closely with Interserve to make sure that any disruption while we work at this particular site is kept to a minimum. If you are going to be directly affected by our work, our site team will let you know in advance. Typical working hours will be Monday to Friday, between 8.00am and 6.00pm. During this work, our vehicles will need access to the sewer pumping station which is located in the field south of Darlington Road. You may see some increase in vehicular movement. Ben Gilbert NWL Project Manager

Project updates

Update by Brian Hall

Hello Folks

Just to let you all know we will be back on site from Monday 2nd September 2019 for around 6 weeks. We will be removing the temporary tank and installing a new tank in its place. So we will have a bit of civil work to do then mechanical and electrical work. There should not be any disruption, we will have one big delivery at some stage to swap the tanks and apart from that just a couple of light vehicles and van deliveries. I will update with some photos when we are back on site.

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

There is currently no activity on site and we are aiming to return to complete work sometime in July. 

The area is very busy at the moment with lorries and construction traffic, this has nothing to do with Interserve or Northumbrian Water. I will update you as soon as possible when we return to site.

Best regards

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello there my name is Brian Hall I am the customer manager for Interserve Construction working for Northumbrian Water on this project in Elton. I have been around the area today meeting residents and leaving letters explaining what will be happening. If you have any questions at all please feel free to call me or e-mail. I will try to be as visible as possible in the village while the work is being carried out and happy to talk to anyone. Likewise our site team are very approachable and enjoy talking about the work. 

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

You may have noticed we are on site now and about to commence work (see photos below)

Hopefully you wont notice much apart from some site traffic pulling on and off and a bit of banging as we start the work off. Please let us know if there is anything causing you a problem

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

All finished at the site for the year; can I thank you all for your cooperation and patience while we have been working here. We will be back in 2019, I will keep you posted on activity. We would all like to wish you a Merry Christmas and a happy new year

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Good morning I am the community officer for Interserve Construction and will be working on this project.

I have been able to meet with some residents and hope to speak to more of you over the next few weeks.

I will be on site on a regular basis and also contactable on 07484 516963 if you would like to speak to me.

I will be posting updates as work continues and introducing other members of the team

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers